Lincoln Hospital Phase 1B Capital Improvement and Infrastructure Upgrades Project, NYC HHC
- Grant & Vine

- Dec 21, 2024
- 1 min read
Updated: Aug 12, 2025

PROJECT DETAILS
CLIENT
LOCATION
New York, NY
CONTRACT VALUE
$38,000,000
GRANT & VINE ROLE
Construction Manager
PROJECT ENGINEER
Various
MAJOR SUBCONTRACTOR/SUPPLIERS
PROJECT STATUS
COD date December 2024
PROJECT DESCRIPTION
Construction Management services oversee the implementation of a capital improvement and infrastructure upgrades program throughout the facility. The project is being completed in ten bid packages and includes the following projects:
Replacement of hospital hospital-wide heating loop piping system, as well as replacement of approx. 500 patient room induction units
Modernization of Elevator Cars 1 – 6, including Code Pink technology
Replacement of all interior and exterior facility lighting systems, including patient room lighting systems, with LED lighting and controls
Replacement of select Air Handling Units
Facility-wide BMS Upgrades
Upgrades to the existing chiller system and compressed air system
Replacement of De Aerator Tank
The majority of the work required for this project was to be completed second shift and weekends over three years. All work within patient rooms required extensive coordination with facility personnel to accommodate closures. Given the extensive coordination efforts, work within the patient rooms was completed in a single 24-hour shutdown.