eBus Charging Infrastructure Project - Phase 3, New York City Transit

  • Writer: Grant & Vine
    Grant & Vine
  • Apr 30, 2025
  • 1 min read

Updated: Jul 27, 2025

PROJECT DETAILS

CLIENT


LOCATION

New York, NY (Multiple Depot Locations)


CONTRACT VALUE

$165,000,000


GRANT & VINE ROLE

Design Build Manager/Construction Manager


DESIGN CONSULTANTS

  • TBD


MAJOR SUBCONTRACTOR/SUPPLIERS


PROJECT STATUS

In design development, construction start is expected in October 2025. Scheduled completion in December 2027.


PROJECT DESCRIPTION

Design Build Manager for the installation of 265 overhead pantograph bus charging systems at three NYCT bus depot locations throughout the Metro NYC area. The project is being implemented in a fast-track format utilizing multiple Design-Build Teams, Heliox and Hitachi charging equipment technology, and INIT Charge Management Software. Work is to take place within the following existing bus depots with strict logistical restrictions:


  • Mother Clara Hale Bus Depot – 32 pantographs

  • Ulmer Park Depot – 113 pantographs

  • Jamaica Depot – 120 pantographs