PROJECT DETAILS
CLIENT
LOCATION
New York, NY
CONTRACT VALUE
$28,000,000
GRANT & VINE ROLE
Construction Manager
PROJECT ENGINEER
Grant & Vine
MAJOR SUBCONTRACTOR/SUPPLIERS
PROJECT STATUS
Completed - April 2025
PROJECT DESCRIPTION
Design and installation of 28 overhead pantograph bus charging infrastructure systems at four NYCT locations – East New York, Herkimer, Kingsbridge, and Williamsburg – utilizing Siemens and ABB systems. The project requires extensive electrical service upgrades as well as new feeder installation. Includes Electrical Distribution Equipment, Charger Branch Circuits, Overhead Charging systems, and associated structural steel gantry components. Work is to take place within existing bus depots with strict logistical restrictions.